Blasting today, September 20 at Kendal

Blasting will be conducted today, Thursday, September 20, at 11:30 a.m. and 2:00 p.m. by Rebel Ridge.


Tuesday, September 18, 2018

Work behind Rebel Ridge


The construction crew will be drilling near Rebel Ridge tomorrow, Wednesday, September 19, and we anticipate blasting on Thursday, September 20.  We will have more information after drilling is completed about specific days/times

No blasting today, September 18

No blasting will be conducted at the Kendal construction site today, Tuesday, September 18.

Thursday, September 13, 2018

No blasting today, September 13

There will be no blasting today, Thursday, September 13, on the Kendal construction site.

Wednesday, September 12, 2018

Blasting today, September 12

Blasting will be conducted today, September 12, at 11:00 a.m. and 1:00 p.m. near Springlot Drive.

Tuesday, September 11, 2018

Monday, September 10, 2018

Wednesday, September 5, 2018

Tuesday, September 4, 2018

Blasting today, September 4

Blasting is scheduled for today, Tuesday, September 4, at 11:00 a.m. and 1:30 p.m. near Springlot Drive.