Blasting on Friday, February 1

We anticipate that there will be blasting at 11:00 a.m.,  1:00 p.m., and 2:30 p.m. on Friday, February 1.  The work will be conducted in the same area as Monday's blasts.

Emails and texts will be sent Friday morning.

Thursday, January 24, 2019

Blasting at Kendal during the week of January 28

We have been fortunate that we have not needed to blast for the last few months.  It has been determined, however, that some additional blasting will be needed at the southeast side of the loop, near Rebel Ridge.  The information provided by the contractor indicates the 300 foot radius does not go past the Kendal property line.  


We anticipate that this will be conducted next week, possibly as early as Monday, January 28.  Texts and e-mails with more specific information will be sent as soon as it becomes available.

Because the blasts have been scaled back, and because of the continual delays due to wet weather, the whole process has taken longer than expected.  We appreciate your patience.

Thursday, January 10, 2019

Kendal construction progress

Significant progress is being made on the construction/expansion project, despite the heavy precipitation of the last few months.

Four of the new cottages on Sunrise Ridge are under roof, and foundations have been poured for several more.  While completing the installation of the infrastructure, unexpected rock was discovered beneath cottages #24 and #25, adjacent to our Rebel Ridge neighbors' properties.  Our construction manager has informed us that drilling and/or some additional blasting may need to occur during the week of January 14.  Additional information will be communicated as it becomes available.

Click the video link below to view last week's drone footage of the cottage site.