Thursday, May 31, 2018

Detention Basin #1 near Confederate Cove


Due to the unusual amount of rain, there may be several more small blasting events before the detention basin can be completed.

Construction update, May 31


We anticipate blasting today, Thursday, May 31, in the afternoon.  The time will depend upon the weather.

Additional information will be posted as it becomes available.

Wednesday, May 30, 2018

Construction Update May 30


The contractors are planning to conduct one blast today in Detention Basin #1 (by Confederate Cove), if the rain holds off.  They anticipate that it will occur at approximately 2:30 p.m.

Tuesday, May 29, 2018

Blasting today, May 29

The contractors have just notified us that they will proceed with blasting this afternoon, most likely between 2 and 3 p.m.  If we get additional information prior to the blast, I will pass it along.

Friday, May 25, 2018

For safety reasons


Just a quick reminder . . .

 

We will all be spending more time outside as the weather improves and children are out of school for the summer.   It is important for everyone’s safety that all of us avoid the Kendal construction area.  No unauthorized visitors should be on any portion of the site that is fenced and/or marked No Trespassing.

 

Thank you for your cooperation.

Thursday, May 24, 2018

Construction Update May 24


There will be no blasting on the construction site at Kendal tomorrow, May 25.  

All work will be suspended on Monday, May 28, for the Memorial Day holiday.

Wednesday, May 23, 2018

Construction Update May 23


There will be no blasting today, Wednesday, May 23.  We anticipate that there will be blasting tomorrow;  more information as it becomes available.