Friday, September 27, 2019

KaLex Construction Project Update


Here is an update on the construction and renovation project at Kendal at Lexington.  The project consists of 6 sub-projects . . .

  • IL Cottages:  All 30 cottages are now under roof and 5 new families have moved in!  We anticipate that 22 of the 30 residences will be occupied by the end of 2019.

  • Emergency access road:  The road has been constructed.  One additional layer of surface and some landscaping will complete that part of the project.  A gate has been installed at the Rebel Ridge Road entrance to prohibit unauthorized use of the road.

  • Borden Health Center:  Construction of the two additions is getting very close to completion and the renovations of the current structure are in “full swing.”

  • Webster Center Assisted Living:  The construction of the addition is behind schedule but making progress. 

  • Maintenance Building: Construction underway.

  • Dining Facility:  The foundation and roof skeleton for the expansion of the dining room is almost complete.  Construction of the walls to close in the new space and interior renovation of the existing space are underway.

Thank you for your patience throughout this work.   We anticipate that the full project will be completed in the spring of 2020.  With the all the cottages under roof and all the utility work having been completed, we do not anticipate any additional blasting.  We do, however, want you to be aware that there is additional paving work to be completed.  Also, final grading and conversion of the sediment ponds to detention ponds will occur towards the end of the project.

Friday, August 16, 2019

Construction Work on Saturday, August 17

Work will be underway on Saturday, August 17, on the cottages on Sunrise Ridge.  There will be no site work, but some framing and interior work on the cottages will be on-going.

Have a great weekend!

Tuesday, July 30, 2019

Work begins on emergency egress road at Kendal


Preliminary preparation for the construction for the emergency egress road off of Rebel Ridge will begin this week. Some of the areas will be fenced off.  For your safety, please do not go into the fenced areas.  These are part of the construction and will be limited to authorized personnel only. 

Thank you for your patience.  We expect this to be completed within a month, weather permitting.

Tuesday, April 23, 2019

Work begins on emergency exit road


Now that the weather has improved, things are going at full-swing on the construction and renovation project.  We all look forward to completion!

Part of the next phase of the project includes beginning work on the emergency exit road.  To accomplish this, we will be required to fence off that area.  We regret any inconvenience, but please be assured that once it is safe again, the fence will disappear and everyone will be welcome.  We ask your cooperation to please respect the posted areas for no trespassing.  They are marked off for everyone’s safety.

Thank you again for your understanding and patience.

Tuesday, March 5, 2019

Blasting on March 6 and 7

There will be two blasts on March 6 and two on March 7, at approximately 11:00 a.m. and 1:00 p.m. each day.  This work will be done at the Rebel Ridge end of the loop road, and the 300' blast area is all on Kendal property.

Thursday, February 28, 2019

Construction progress report

Construction and renovations are progressing at Kendal.  Renovations at the Borden Center have been completed in one hall and crews are working on the second one, and construction of the additions for the new spaces at the nursing home is well underway.

Simultaneously, renovations of the Webster Center are proceeding, and construction of the new cottages is moving ahead.  It's a busy place!

We have been informed by our contractors that minimal blasting may be needed next week, probably towards the middle of the week.  This work will be conducted on the loop road, towards the Rebel Ridge end of the loop.

Additional information will be forwarded as soon as it becomes available.

Thursday, January 31, 2019

Blasting on Friday, February 1

We anticipate that there will be blasting at 11:00 a.m.,  1:00 p.m., and 2:30 p.m. on Friday, February 1.  The work will be conducted in the same area as Monday's blasts.

Emails and texts will be sent Friday morning.