Friday, October 19, 2018

Monday, October 15, 2018

No blasting October 15 and 16

There will be no blasting on the Kendal construction site on Monday, October 15 and Tuesday, October 16.

Friday, October 12, 2018

Storm Update


Kendal at Lexington staff spent this fair weather day conferring with representatives from the City of Lexington, Rockbridge County, Dominion Power, Spectrum engineers, and the Nielsen construction team to evaluate the impact of yesterday’s torrential rains on our construction project.  We have been very fortunate to have experienced limited damage. 

We expect that recommendations regarding our storm water management system to be forthcoming and electrical repair work on our campus to occur next week.  We will provide additional information as it becomes available. 

Thursday, October 11, 2018

Statement of Kendal at Lexington Regarding Flooding Due to Heavy Rain


October 11, 2018
3:00 pm
Due to the unusual amount of rainfall, there has been a breach of water retention mechanisms on Kendal’s construction worksite and water is flowing into some neighboring areas. Kendal at Lexington regrets this situation and is actively working with the City of Lexington, project contractors and engineers to assess and alleviate the issue.
Per requirements, sediment basins are designed to contain 134 cubic yards of water per acre of disturbed area. The water management installations were designed in excess of that requirement.  It is suspected the torrential rains we received today were of an historic nature and exceed expectations.

Kendal at Lexington’s property has been affected as well.  All hands are on deck to address the situation.

Please contact Executive Director Mina Tepper at (540) 463-1910 with questions or concerns.  Updates will be posted on the blog at http://kalexmasterplanupdate.blogspot.com.

Monday, October 8, 2018

Blasting today, Monday, October 8

One blasting event is scheduled for today, Monday, October 8, at 2:00 p.m. near the center of the loop road.

Thursday, October 4, 2018

Kendal's Construction Update Blog


This blog was created to post photos and updates of the progress on our current expansion and renovation project.  We have discovered that this is not an ideal venue for communicating time sensitive information as it only updates once a day.  Blasting notices will continue to be posted as promised, but please make sure you are included in the e-mail or text list if you want timely notices.  You can contact Becky Edmondson at bjedmondson@kalex.kendal.org or (540) 458-3782 to be added to these lists.

Stay tuned for more interesting information about the construction project!

Wednesday, October 3, 2018

Blasting today, October 3

Blasting is anticipated at approximately 11:30 a.m. and 2:00 p.m. today, October 3, near Rebel Ridge.

Monday, October 1, 2018

Blasting today, October 1

Blasting will be conducted near Rebel Ridge today at approximately 11:00 a.m. and 2:00 p.m.