August 30 blasting postponed to August 31

The contractors have just notified us that the blasting scheduled for August 30 has been postponed until August 31.

Wednesday, August 29, 2018

Blasting scheduled for Thursday, August 30


On Thursday, August 30, blasting will be conducted near Springlot Drive on the Kendal campus at 10:00 a.m., 12 noon, and 2:30 p.m.

No blasting today, Wednesday, 8/29 at Kendal

There will be no blasting today at Kendal. Wednesday,  8/29.

Tuesday, August 28, 2018

Construction update 8/28


 

 

 

 

 

 

The construction crews have identified a rock formation that must be removed in order to install sewer and water infrastructure in an area on the Kendal property that abuts the homes on Rebel Ridge Road.  Having weighed the options, it has been determined that blasting will be used to remove the rock.  

The contractor has made arrangements for additional surveys to be conducted on the homes located at 112, 110, 108, 106, and 104 Rebel Ridge Road even though they are located outside the 300 foot blast radius.  The surveyors plan to be in the neighborhood on Friday, August 31st to perform the surveys.

Blasting is likely to begin after Labor Day and will continue intermittently for about two weeks.  The blasting contractor will adhere to all previously established blasting protocols. 

Regular updates regarding blasting activity are communicated via the Kendal Construction Blog and using email and text messaging.  To receive communications from Kendal please provide your email address and/or phone number for texting to Julia Skare, the Owners Representative for Kendal.  Julia may be reached by phone at 434-390-8956 or by email at juliaskare@gmail.com.  Please do not hesitate to reach out to Julia if you have questions or concerns regarding the project.

Friday, August 17, 2018

Saturday, August 18

Weather permitting, work will continue on the Kendal construction site on Saturday, August 18.

Thursday, August 16, 2018

Wednesday, August 15, 2018

Tuesday, August 14, 2018

Blasting today, August 14

Blasting will be conducted at Kendal today at 11:30 a.m. and 2:30 p.m. near Springlot Drive (close to the Webster Center.)

Monday, August 13, 2018

Blasting postponed until Tuesday, August 14

The blasting event that was scheduled for today has been postponed until tomorrow, Tuesday, August 14.  This will be conducted close to Springlot Drive which is close to the Webster Center on the Kendal campus.

Friday, August 10, 2018

Blasting anticipated next week

Blasting is expected near Springlot Drive next week.  More details as they become available.

Work on Saturday, August 10

The construction crew will be working on Saturday, August 10.

Construction Update August 10, 2018


Excavation for the Cottages and Main Facility sites continues.

 

Installation of water main has begun for the Cottages, several cottage pad sites are complete, and the first foundation is planned to be poured August 10. 

 

Work to break up the rock on Sediment Basin #2 (Rebel Ridge area) continues. The excavation of the pond is expected to continue for the next couple of weeks.

 

Blasting is expected to resume the week of August 13, with the blast to take place in the vicinity of  the Cottage site construction trailer.  

 

A determination as to additional need for blasting for the stormwater, sanitary and water main installation at the east end of the property (Rebel Ridge area) and adjacent to the Health Centers is pending. All options are being considered. 

Friday, August 3, 2018

Work on Saturday, August 4

Weather permitting, work will continue on the Kendal construction site on Saturday, August 4.