Friday, August 10, 2018

Construction Update August 10, 2018


Excavation for the Cottages and Main Facility sites continues.

 

Installation of water main has begun for the Cottages, several cottage pad sites are complete, and the first foundation is planned to be poured August 10. 

 

Work to break up the rock on Sediment Basin #2 (Rebel Ridge area) continues. The excavation of the pond is expected to continue for the next couple of weeks.

 

Blasting is expected to resume the week of August 13, with the blast to take place in the vicinity of  the Cottage site construction trailer.  

 

A determination as to additional need for blasting for the stormwater, sanitary and water main installation at the east end of the property (Rebel Ridge area) and adjacent to the Health Centers is pending. All options are being considered. 