Here is an update on the construction and renovation project at Kendal at
Lexington. The project consists of 6 sub-projects . . .
- IL
Cottages: All 30 cottages are now under roof and 5 new families have
moved in! We anticipate that 22 of the 30 residences will be
occupied by the end of 2019.
- Emergency
access road: The road has been constructed. One additional
layer of surface and some landscaping will complete that part of the
project. A gate has been installed at the Rebel Ridge Road entrance
to prohibit unauthorized use of the road.
- Borden
Health Center: Construction of the two additions is getting very
close to completion and the renovations of the current structure are in
“full swing.”
- Webster
Center Assisted Living: The construction of the addition is behind
schedule but making progress.
- Maintenance
Building: Construction underway.
- Dining
Facility: The foundation and roof skeleton for the expansion of the
dining room is almost complete. Construction of the walls to close
in the new space and interior renovation of the existing space are
underway.
Thank you for your
patience throughout this work. We anticipate that the full project
will be completed in the spring of 2020. With the all the cottages under
roof and all the utility work having been completed, we do not anticipate any additional
blasting. We do, however, want you to be
aware that there is additional paving work to be completed. Also, final grading and conversion of the sediment
ponds to detention ponds will occur towards the end of the project.